Time and Work - General Questions
Rs. 430 |
Rs. 450 |
Rs. 400 |
Rs. 500 |
C's 1 day's work = 1/3 - (1/6 + 1/8) = 1/3 - 7/24 = 1/24
A's wages : B's wages : C's wages = 1/6 : 1/8 : 1/24 = 4 : 3 : 1
C's share (for 3 days) = Rs. (3 x 1/24 x 3200) = Rs. 400
12 days. |
15 days. |
10 days |
20 days |
A's 2 day's work = (1/20 x 2) = 1/10
(A + B + C)'s 1 day's work = (1/20 + 1/30 + 1/60) = 6/60 = 1/10
Work done in 3 days = (1/10 + 1/10) = 1/5
now, 1/5 work is done in 3 days
∵ Whole work will be done in (3 x 5) = 15 days.
2/7 |
1/4 |
8/15 |
5/12 |
A's 1 day's work = 1/15
B's 1 day's work = 1/20
(A + B)'s 1 day's work = (1/15 + 1/20) = 7/60
(A + B)'s 4 day's work = (7/60 x 4) = 7/15
∵ Therefore, Remaining work = (1 - 7/15) = 8/15
30 days |
10 days |
7 days |
22 (1/2) days |
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes (3/2 x 60) = 90 days
So, A takes 30 days to do the work.
⟹ A's 1 day's work = 1/30
⟹ B's 1 day's work = 1/90
⟹ (A + B)'s 1 day's work = (1/30 + 1/90) = 4/90 = 2/45
∵ A and B together can do the work in 45/2 = 22 (1/2) days.
9 days |
9 (3/5) days |
4 days |
15 days |
(A + B + C)'s 1 day's work = 1/4
A's 1 day's work = 1/16
B's 1 day's work = 1/12
and, (200/X + 400/Y) = 25/3
∵ C's 1 day's work = 1/4 - (1/16 + 1/12) = (1/4 - 7/18) = 5/48
⟹ So, C alone can do the work in 48/5 = 9(3/5) days.